Case study from the founder's experience
Establishing an enterprise PMO in a government entity
Place in the vertical integration chain: Project management
Context
A government entity that does not execute its projects itself: as the owner, it receives them from suppliers and contractors, across a large portfolio spanning several sectors.
Challenge
Unified management of the portfolio, linked to senior leadership and covering the project cycle from tendering to acceptance and payment.
How the work ran
- Design
An operating model with three sections, project governance, project support and supplier relations, reporting directly to the CEO. A three-level escalation path with handling times set by impact: 5 working days for low impact, 3 for medium and 2 for high.
- Build
A PMO manual written as a governance document of 12 sections, and an approved procedures manual of 24 procedures.
- Activate
Direct management of every project within the PMO's mandate.
- Measure
A recurring statistical report on the workforce deployed on projects, with eight indicators.
Outputs
- Operating model and structure
- PMO manual
- Procedures manual
- Escalation path and handling times
- Projects workforce database and recurring statistical report
What the organization can now do
The entity now has one unit that follows all its projects and measures their performance, with approved procedures and a clear escalation path up to the CEO.
A project in which the founder served as consultant, not contracted directly by VIC. The client is not named.
Other case studies
- 4A methodology for developing the institutional strategy of a government entity
- 55Linking the operational plan to the OKR methodology and performance indicators
- 12Measuring PMO value and maturity with the PMO Value Ring
- 6Training built on measured competency gaps
- 20Inventory of critical PMO knowledge in response to an internal audit finding